MANUFACTURED HOME ADU TIMELINE

 

RESEARCH

DAY 0

Learn all you can about local codes and ordinances as well as your specific site characteristics and challenges. Visit the Planning Dept of your City or County to learn about the application process, costs and reasonable timeline expectations.

4 Weeks
 

BUDGETING

DAY 28

Put together an all-inclusive budget so that you can determine if it is feasible to take on your project given all of the factors involved. Use tools like our Interactive Calculator as a guide but understand that every situation is different. Make sure not to overlook the additional cost of items outside of the building like parking pads and landscaping.

2 Weeks
 

FINANCING

DAY 42

Meet with 21st Mortgage and other lenders that can go over the various financing options available to you. Review those options with your trusted tax advisor. Budget for optional items not included in the home price that you will have to pay for after taking possession of your new home.

4 Weeks
 

PLACE YOUR ORDER

DAY 70

Sit down with us and go over every detail to make sure your new home perfectly suits your current and anticipated needs, and also includes the options and amenities important to your quality of life.

1 Week
 

SITE PREPARATION AND PERMITTING

DAY 77

Engineers and Contractors will perform required tests and prepare the home site for its permanent foundation and all utility hookups. Permitting and Inspections are usually the "wildcard" in your project timeline. Although our homes benefit from being built to the strict HUD standards, we still work very closely with the Engineering, Utility Companies and others involved in the infrastructure items.

3 Months
 

DELIVERY

DAY 167

We're almost finished! Our Transportation Dept will coordinate with CHP, CalTrans and Local authorities to get the permits needed to move your home from the factory to your build site. Every delivery is unique due to overpass restrictions, road widths, and accessibility from the freeway to your home site. Some sites will require that we use a crane to lift your home into position.

1 Day
 

FINISHING

DAY 168

We will join sections if appropriate. We'll connect, test and get final approvals on all utilities. We'll assist you to coordinate any landscaping or other contractors you've hired and add time to the timeline if necessary.

12 Weeks
 

COO

DAY 252

That stands for CERTIFICATE OF OCCUPANCY which also means it's time for a big HOORAY! Your new home is finished and approved for occupancy! Here's where we throw a big party and hand the Keys over to you.

Done
?