MANUFACTURED HOME ADU TIMELINE
RESEARCH
Learn all you can about local codes and ordinances as well as your specific site characteristics and challenges. Visit the Planning Dept of your City or County to learn about the application process, costs and reasonable timeline expectations.
4 WeeksBUDGETING
Put together an all-inclusive budget so that you can determine if it is feasible to take on your project given all of the factors involved. Use tools like our Realtime Estimator as a guide. Make sure not to overlook the additional cost of items outside of the building like parking pads and landscaping.
2 WeeksFINANCING
Meet with our Preferred lenders and others that can go over the various financing options available to you. Review those options with your trusted tax advisor. Budget for optional items not included in the home price that you will have to pay for after taking possession of your new home.
2 WeeksPLACE YOUR ORDER
Sit down with us and go over every detail to make sure your new home perfectly suits your current and anticipated needs, and also includes the options and amenities important to your quality of life.
1 WeekSITE PREPARATION AND PERMITTING
Our Build Team will get to work preparing site plans and commencing the permitting process with your city or county. Once approved, our factory will start building your new home while the build team gets busy on preparing the build site for your new home. They'll also be working closely with your utility companies and others involved with the infrastructure items.
3 MonthsDELIVERY
Our Transportation Dept will coordinate with CHP, CalTrans and local authorities to get the permits needed to move your home from the factory to your build site. Every delivery is unique due to overpass restrictions, road widths, and accessibility from the freeway to your home site. Some sites will require that we use a crane to lift your home into position.
3 DayFINISHING
We will join sections if appropriate. We'll connect, test and get final approvals on all utilities. We'll get approvals on all permits and inspections. We'll coordinate with landscaping or other contractors to get your build site looking fantastic.
2 MonthsCOO
That stands for CERTIFICATE OF OCCUPANCY which also means it's time for a big HOORAY! Your new home is finished and approved for occupancy! Here's where we throw a big party and hand the Keys over to you.